Defect library
Mechanical & electrical snags at handover
Mechanical and electrical services in commercial buildings need commissioning records and O&M manuals as well as working equipment. Many of these entries are about paperwork and labelling that should be in place before the client takes the building over.
Updated 19 October 2026
SiteSnag’s library has 11 entries under mechanical & electrical, and 1 of them are marked as safety or critical items. They’re listed below with the most serious first. Each one gives the wording an inspector would put in a report and the trade that would fix it, and 4 carry a reference to the standard or guidance they relate to. The references help you look up the relevant section and aren’t a statement that a particular home does or doesn’t comply.
All 11 entries
Legionella risk (dead legs / TMV)
SafetyDead legs or unserviced TMVs present a Legionella risk. Remove dead legs and service TMVs.
- Trade
- Plumber
- Reference
- HSE ACoP L8
Air conditioning not working / leaking
MajorAC unit not cooling/heating or leaking. Investigate and repair.
- Trade
- Mechanical
- Reference
- None listed
Fan coil condensate leak
MajorCondensate leaking from fan coil unit. Repair drain and replace damaged tiles.
- Trade
- Mechanical
- Reference
- None listed
Ventilation not commissioned
ModerateVentilation air flows not balanced or commissioning records missing. Commission.
- Trade
- Mechanical
- Reference
- Approved Document F
Lighting controls not working
ModeratePIR/daylight/DALI lighting controls not working as designed. Commission.
- Trade
- Electrician
- Reference
- None listed
Containment / cable tray not secured
ModerateCable containment unsupported or lids missing. Secure.
- Trade
- Electrician
- Reference
- BS 7671
BMS not commissioned
ModerateBuilding management system not commissioned or not reporting. Commission.
- Trade
- M&E contractor
- Reference
- None listed
O&M manuals / test certificates outstanding
ModerateOperation and maintenance manuals or test certificates not provided. Provide.
- Trade
- M&E contractor
- Reference
- None listed
Plant room access / housekeeping
ModeratePlant room cluttered, unlit or lacks safe access. Rectify.
- Trade
- M&E contractor
- Reference
- None listed
Distribution board schedule missing
MinorCircuit schedule missing from distribution board. Provide.
- Trade
- Electrician
- Reference
- BS 7671
Services not labelled
MinorPipework, valves or isolators not labelled. Label to specification.
- Trade
- M&E contractor
- Reference
- None listed
Using these in a report
In the SiteSnag app, starting to type a defect title in the camera brings up these entries. Picking one fills in the description, severity, trade and reference, and you can edit the wording or add your own defects to the library. Every snag then goes into the branded PDF report with its photos and a numbered pin on the floor plan.
For a room-by-room walk-round, use the new build snagging checklist, or go back to all defect categories.
Other categories
Previous: Commercial fit-out (10). Next: Lifts & doors (5).
- Decoration (20)
- Walls & ceilings (19)
- Doors & joinery (38)
- Windows & glazing (22)
- Floors (16)
- Tiling (12)
- Kitchen (42)
- Bathroom (29)
- Plumbing (17)
- Heating (15)
- Electrical (28)
- External (33)
- General (9)
- Ventilation (6)
- Insulation & damp (10)
- Roofing (18)
- Drainage (8)
- Garage (5)
- Fire safety (17)
- Accessibility (8)
- Commercial fit-out (10)
- Lifts & doors (5)
- Car park & external works (7)
- Signage & security (6)
- Fitted furniture (7)
- Stairs (6)
- Structure (8)
- Timber & pests (8)
- Communal areas (6)